Extension of time request
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. In the United States, this is described as a time extension. The UK equivalent is an extension of time (EOT). Fore more information see: Extension of time.
Time extensions may be granted if the contractor can demonstrate that the delay was caused by events beyond their control. The contract will typically specify the circumstances and format in which a time extension request may be made.
A request will commonly include the following details:
- The delay that has been incurred and the affected activities.
- The specific issues that caused the delay.
- What steps have been taken to mitigate the delay.
- Schedule or cost adjustments that have been made to try and reduce the impact of the delay.
- The contract clause that allows the request.
- The amount of time being requested (in calendar days) and the proposed recovery plan.
- Supporting documents, such as; photographs, video footage, timesheets, and so on.
- Evidence of communications warning of possible delays.
In submitting the time extension request, the contractor must consider that calendar days are not the same as working days, that insurances and other bonds may need to be re-issued to cover any agreed extension period, and no further time will need to be requested relating to the same events.
If they approve the request, the project manager must reply by letter and issue a change order. The contract may specify a time frame within which time extension requests should be submitted and a response issued.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherit assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.


















